Top 10 Purple Line News Stories of 2016!

Purple Line Year in Review

As we close the book on 2016, it’s time once again for our annual look back on the Purple Line news stories that made headlines in the past 12 months.

When 2016 began, we had high hopes that this would be the year that the project finally broke ground, but as in life, things don’t always work out the way you plan. Despite the setback, the Purple Line made tremendous progress this year and we are only one step away from achieving our goal.

The New Year brings new hope that the federal lawsuit that is holding up construction on the project will be resolved, and that a year from now, our year in review will be filled with stories about the construction that is taking place across the corridor. So, without further ado, we present to you the top ten Purple Line news stories of 2016!

10. Purple Line Railcars Unveiled

In the spring, the concessionaire, Purple Line Transit Partners, released the first renderings of the railcars that the Purple Line will be utilizing. At 136 feet in length, the Purple Line light rail vehicles will be the longest transit railcars in America, edging out Austin's cars by 2 feet! Each railcar is expected to have 80 seats, as well as space for up to eight wheelchairs and eight bicycles. Also, unlike Metro railcars which we are accustomed to, the trains will have an open gangway design, meaning that you will be able to walk from one end of the train to the other with ease.

9. Apex Building Redevelopment On Track

The potential redevelopment of the Apex Building has been a perennial feature on our list of the top ten Purple Line stories, but what once seemed like a longshot is starting to look like a real possibility. In 2016, a developer acquired the Apex Building, paving the way for it to be redeveloped and for the Capital Crescent Trail (CCT) to be rebuilt along with and under it. The building is slated to be demolished in early 2017, which will result in an improved Purple Line station and CCT tunnel. Just this month, the Montgomery County Council approved funding to keep the Capital Crescent Trail underground, and to widen it to 16 feet through the length of the tunnel.

8.  UMD Students Ride for Free

Big news was made at Purple Line NOW’s first forum in its envisioning the Purple Line series in College Park this past spring, and it had the students cheering. University of Maryland officials confirmed that there will be a “fare-free zone” for students between the Adelphi Road/West Campus station and the M Square stop just south of the College Park Metro station. The fare-free zone will enable students and faculty with a University ID to ride the Purple Line for free, not to mention reduce the time it takes to traverse the sprawling campus.

7. Fence Fight in Chevy Chase Resolved

As we all know, a lawsuit filed by opponents of the Purple Line has delayed the project’s groundbreaking, but another long-running court case was resolved in the Purple Line’s favor in 2016. In January, Maryland’s highest court ruled that homeowners adjacent to the Capital Crescent Trail cannot claim ownership of the land. Since then, the county has been working with residents to remove any fences or sheds that lie in the Purple Line’s path before construction begins.

6. Counties Cement Their Commitment to the Purple Line

In 2016, Montgomery and Prince George’s Counties both formalized what they had agreed to do in 2015, which is contribute some additional county dollars to make the project a reality. In November, the voters in Prince George’s County overwhelmingly approved a bond measure to fund the county’s additional commitment. And in May, the Montgomery County Council approved its additional contribution to the project in the county’s capital improvements program.

5. Scope Changes Revealed

As final design nears completion, we have gotten a closer glimpse of how the Purple Line will integrate with existing communities around station areas. In Riverdale Park, there was pushback against eliminating a planned aerial bridge at the station and replacing it with a fill wall to reduce the project’s overall costs. However, Prince George’s County officials have expressed confidence that the issue will be favorably resolved. And in Silver Spring, we got a glimpse of how the Purple Line will integrate with the Silver Spring Transit Center. And earlier this month, the state and concessionaire presented renderings of the stations at the Art-in-Transit public meetings.

4. Pre-construction Activities Begin

The pending lawsuit against the Purple Line may have delayed the ceremonial groundbreaking, but it hasn’t prevented preconstruction activities from commencing along the corridor. At this time, the pre-construction work mostly consists of soil borings at various locations to give the state and concessionaire a better understanding of underground conditions. You can keep up to date on the latest pre-construction activity at the official purple line website:http://www.purplelinemd.com/en/pre-construction/updates-and-notices

3. Financial and Commercial Close Reached

In the spring, the state finalized the P3 agreement for the Purple Line. First, they reached commercial close on the project when the Board of Public Works voted unanimously to approve the $5.6 billion contract for the Purple Line. Thereafter, in late June, the Purple Line reached financial close when Purple Line Transit Partners secured and signed the financing agreements for the project. PLN dedicated its second forum in its Envisioning the Purple Line series to the P3 deal in order to help the public better understand how it will help keep the project under budget and on time.

2. Concessionaire Selected

When we turned the calendar to 2016, four teams of concessionaires had submitted bids for the right to be the state’s partner on the Purple Line. In March, the state announced that it had selected Purple Line Transit Partners to build, operate and maintain the Purple Line for 30 years. The state also announced that it had worked with the concessionaire to reduce the project’s costs by over $500 million dollars. MTA chose the winner in part because of the real world experience on the first of its type Denver Eagle Commuter rail project. PLN’s third forum in the Envisioning the Purple Line series took a closer look at the Purple Line’s elder siblings, which began operations on schedule this May.

1. Federal Lawsuit Delays Groundbreaking

The number one Purple Line story in 2016 has undoubtedly been the federal lawsuit that has left the project in limbo. In August, a U.S. District Court Judge ruled that the Federal Transit Administration did not adequately consider the impact that Metro’s recent woes might have on the Purple Line’s ridership. Unfortunately, in late November, the judge reaffirmed his previous ruling that construction cannot proceed, but he did present a path forward for the FTA to present updated information which could show that the FTA factored Metro’s issues into its ridership projections. On Friday, December 16, the FTA released its findings: the Purple Line’s benefits are substantial and sufficient even setting aside transfers to and from Metro! If the judge rules promptly, the outstanding issues could be resolved before the end of winter.

And with that terrific news, we close the year with thanks to you, our most ardent supporters, for all you do for the project and Purple Line NOW. As always, we appreciate your support and ask you to keep us in mind as you make your end-of-year contributions. Here's to 2017 - the year the Purple Line finally breaks ground!