Purple Line NOW News - April 12, 2023

In today's edition of Purple Line NOW News, here's what you'll find:

  • What's Happening at PLN?
    • Are You a Purple Line NOW Donor?
  • Happening Along the Purple Line Corridor
    • Maryland’s WMATA Headquarters Open at New Carrollton
  • Construction Updates and Project Features
    • 2026 Opening for Purple Line Confirmed
    • OMF Progress

Share This Newsletter

Please feel free to share this newsletter - no permission from us needed! You can always find a link to our newsletter on our Purple Line NOW website which makes it easy to share with your friends, neighbors, constituents, customers, and employees.

What' Happening

   WHAT'S HAPPENING AT PLN?

Are You a Purple Line NOW Donor?

We are so appreciative of each and every dollar that comes to us by way of a donation. We are a nonprofit organization that relies on donors to continue its mission and we cannot exist without your generosity each and every year. Your donation will be noted on our website and in all printed materials and at all events for a year following your contribution to Purple Line NOW. Curious as to when you last made a donation to us? You can check out our website or shoot us an email. If you don't see your name listed, we hope you will consider donating to our organization when you are able. Thank you, thank you.

DONATE

 

Features and Highlights

   HAPPENING ALONG THE PURPLE LINE CORRIDOR

Maryland’s WMATA Headquarters Open at New Carrollton

In a Twitter video release, Maryland’s Governor Wes Moore celebrated the opening of the Metro Building at the New Carrollton station which will house a variety of businesses and organizations, along with the Maryland WMATA Headquarters, including 1,200 WMATA employees. According to a press release issued by WMATA, the ribbon-cutting ceremony that brought together the Governor along with many other elected officials, the building “marks the continued transformation of New Carrollton as a transit-accessible hub for office space, housing, and retail.”

Construction Updates

   CONSTRUCTION UPDATES & PROJECT FEATURES

2026 Opening for Purple Line Confirmed

In January of this year, the Washington Post reported that the project could sustain yet another hurdle, pushing opening day for passenger service into mid-2027. (K. Shaver. “Maryland’s Purple Line construction faces another seven-month delay.” Washington Post, 19 January 2023.) Just last week, however, we were delighted to learn that the project is instead on target to open in fall 2026! (G. Bixby. “Purple Line slightly less delayed, on target to open in fall 2026, spokesperson says.” MoCo360, 5 April 2023.)

OMF Progress

It has been amazing to watch the Operations and Maintenance Facility come to life over the past few years. On their Twitter feed, MDOT says that their crews have installed track in the wash bay and poured the concrete to embed the track. The facility will be used to service and store the 140-foot vehicles when they arrive.

Photos From Around the Corridor


Photo Courtesy: MDOT MTA

Photo Courtesy: MDOT MTA

Photo Courtesy: MDOT MTA

Stay Connected

   STAY CONNECTED

Get Connected

Make sure you are signed up for timely alerts from Purple Line NOW via our Twitter and Facebook pages, and at our website Purple Line NOW.

Facebook Twitter

Follow Us

 Follow Us on Facebook Follow Us on Twiter

Donate Now Contact Us e-News