For immediate release: February 9, 2024

Metro announces three-year capital construction plans, including Red Line station closures this summer

Metro has announced plans for major capital construction over the next three years to modernize the Metrorail system, improve safety and reliability, and maintain a state of good repair. Planned closures are scheduled between summer 2024 and summer 2026, with additional construction planned over the winter holidays.

Beginning in early June, Glenmont, Wheaton, Forest Glen, Silver Spring and Takoma stations on the Red Line will be closed. The closure will continue through early September with the possibility of reducing the work zone to allow Takoma Station to reopen prior to the end of construction.

The planned work includes upgrading the signaling system, installing communication and train control cables, and repairing the interlocking; which allows trains to cross from one track to the other outside the Takoma Station. Detailed service plans, including free express and local shuttle buses, are being developed and will be announced at least one month prior to the start of the closure.

2024 Red Line Closure Glenmont to Fort TottenThe work is being planned in coordination with the Maryland Transit Administration Purple Line Project to build a new mezzanine on the platform at Metro’s Silver Spring Station to provide easier access between Metro and the future MTA Purple Line. The Maryland Purple Line light rail line is not part of the Metrorail system, but building the new connection between the two will require the use of both tracks for an extended period and can’t be completed safely and timely with single tracking only.

Additional work includes leak mitigation, automatic train control system replacements, traction power cables installation, drain pumping station replacement, tunnel standpipe replacement, and elevator and escalator maintenance.

Improvements in planning and scheduling track work through summer, winter, and extended weekend outages instead of extensive single tracking, has also helped reduce the amount of planned service disruptions. In the past seven years, the impact to budgeted service declined by half to just four percent with more weekends free of track work on almost all lines.

 

Following the Red Line closure this summer, major construction is also planned:

December 2024 – January 2025

Blue Line Orange Line Silver Line Construction Foggy Bottom – GWU to L’Enfant Plaza
Duration: Approximately two weeks

  • Farragut West, McPherson Sq, lower level of Metro Center (upper-level Red Line open), Federal Triangle, Smithsonian stations affected
  • Pour new grout pads and replace fastener replacements to provide smooth, safe rides
  • Includes 6,400 linear feet of grout pad and fastener replacement
  • Installation of 15,000 linear feet fiber optic cable for communication and train control
  • Construction will require isolated closures, but not the full segment between all stations. Developing plans and analysis to close smaller segments and/or single tracking.
  • Alternative to planned work - four months of weekend single tracking, or up to 400 late-night single tracking

Summer 2025

Blue Line Construction Franconia-Springfield to King Street
Duration: Approximately three weeks

*Exact dates and order of outages to be determined

  • Van Dorn St and Franconia-Springfield stations closed
  • Upgrade train control system
  • Replace worst performing, obsolete signal system
  • System upgrades will bridge to potential next generation signaling system
  • Alternative to planned work – 10 weekend outages and 10 weeks of early weekday closures

Green Line Construction Congress Heights to Branch Avenue
Duration: Approximately six weeks

*Exact dates and order of outages to be determined

  • Southern Ave, Naylor Road, Suitland, and Branch Ave stations closed
  • Install 52,000 linear feet of radio and ancillary fiber optic cable for communication and train control system
  • Required modernization project to improve communications and address FTA findings
  • Repair elevated tracks and bridge
  • Alternative to planned work - seven months of consecutive weekend outages

*All work will be completed before Labor Day with no construction Jul. 4

Winter 2025 – Winter 2026

Green Line Yellow Line Construction L’Enfant Plaza to Fort Totten
*Exact dates and duration to be determined

  • Replace grout pad and fasteners
  • Install fiber optic cable for communication and train control system
  • Replace running rail and repair restraining rail
  • Install signals along tracks to support train control system upgrades
  • Stations served by 82 percent more trains than the system average
  • Developing construction plans to optimize service which may include smaller closures, single tracking, or combination of both

Summer 2026

Red Line Construction Friendship Heights to Grosvenor-Strathmore
*Exact dates and duration to be determined

  • Medical Center and Bethesda stations closed
  • Construction to connect Maryland’s MDOT MTA Purple Line with the Bethesda Metrorail Station
  • MDOT MTA Purple Line currently scheduled to begin operating mid-2027

For updated information on upcoming major construction, follow us on X @wmata @metrorailinfo @metrobusinfo, sign up for Metro Alerts text and email messages, or contact our customer service team. Representatives are available weekdays 7 a.m. – 8 p.m. and weekends 8 a.m. – 8 p.m. and respond to chat, email, and our social media channels.