History of the Georgetown Branch
  1. 1910 - The B&O Railroad completed a branch line to Georgetown. “The Georgetown Branch” leaves the CSX main line at a junction in the North Woodside area of Silver Spring, arcing westward through Lyttonsville, Chevy Chase Lake and Bethesda and on southward to the federal heating plant in Georgetown.

  2. 1970's - A graduate student at the University of Maryland writes a thesis proposing use of the Georgetown Branch right-of-way for a rail transit system to connect Silver Spring and Bethesda.

  3. 1978 - The North Silver Spring Sector plan is amended to include a reference to the potential use of the Georgetown Branch right-of-way for transit.

  4. 1985-86 - The CSX railroad files intent to abandon the Georgetown Branch right-of-way.

  5. Nov. 1986 - The Montgomery County Council approves Georgetown Branch Master Plan Amendment designating the right-of-way “a public right-of-way intended to be used for public purposes such as conservation, recreation, transportation, and utilities. It is not to be used for a continuous roadway”.

  6. Dec. 1988 - Montgomery County purchases the Georgetown Branch for $10.5 million under the National Trails Act which has rail-banking as a major goal.

  7. 1998-99 - The Georgetown Branch Corridor Study is completed, with DeLeuw Cather/Parsons Brinkerhoff serving as the primary consultant. A three-tiered task force worked with the County during this process: a Technical Advisory Committee, a Citizens Advisory Committee, and a Steering Committee.

  8. Dec. 1989 - The County Council approves Georgetown Branch Master Plan Amendment. (Highlights of the Master Plan Amendment are included below).

  9. 1989-90 - Governor William Donald Schaefer offered $70 million to Montgomery County for construction of the Trolley line, but the project floundered when the state determined that the cost would exceed $100 million. During this period a new County Council and County Executive are elected.

  10. 1990 and 1994 - For these two elections, opponents of the trolley (SMART-PAC) raised and distributed campaign contributions of $21,000 and $22,000 respectively. The project stalls.

  11. 1994 - Maryland Mass Transit Administration (MTA) begins a Major Investment Study (MIS) for the Georgetown Branch Transitway/Trail in conjunction with a Draft Environmental Impact Statement (DEIS). A public hearing is held with strong support for the light rail alternative.

  12. 1995 - Newly elected County Executive Doug Duncan recommends that funds be diverted from the Georgetown Branch study to a study of a busway on U.S. 29. The Georgetown Branch DEIS documentation is issued but the project is put on the shelf without a Final Environmental Impact Study FEIS). The U.S. 29 busway proposal fizzles.

  13. Dec. 1998 - A newly elected County Council votes in the first hour of their new term to request priority funding for the Georgetown Branch FEIS.



68,000 riders each weekday is huge! Counting down to completion of Purple Line DEIS; Latest news: Latest News; How you can help



See: Calendar of Events.