We Respond to This Morning's News...

We are committed to bringing you as much information as we can when news breaks about the Purple Line. The news over the past few days has contained a confusing mix of updates on the progress of negotiations between Maryland and the concessionaire, as well as the concessionaire and the builders. Our reaction to this morning’s news in the Washington Post (K. Shaver, Purple Line Consortium Will Dissolve P3 If Deal Not Reached, June 24, 2020) encourages all parties involved to find a way forward to complete the project.

Purple Line NOW Vice President Greg Sanders emphasized one critical constant, “The Hogan administration, the concessionaire, and key state, county, and local leaders are all agreed on their confidence in the Purple Line and of the importance of completing it in a timely manner.” The secrecy and sometimes brinkmanship involved in negotiations often mean that we only learn details in dribs and drabs, with good news reported one day and use of harder line negotiating tools the next. What is clear is that the best outcome remains a settlement with the concessionaire, but failing that, Maryland has options to ensure completion of the light rail project. Sanders added, "finding a path forward has to be the top transportation priority for the Hogan Administration, as an unnecessary delay extends the present disruption while putting off the great benefits that will come when we can all ride the Purple Line."

Purple Line NOW will continue to actively track these issues as they develop. In the meantime, President Ralph Bennett called on all parties to live up to their public statements, “The fundamental strengths of the Purple Line for providing mobility and fueling economic growth remain undiminished. We call on all parties to not be distracted by casting blame and to live up to their commitment to find a way to quickly complete construction while being good stewards of the resources provided by the people of Maryland.”


Purple Line NOW News - June 18, 2020

In today's edition of Purple Line NOW News, here's what you'll find:

  • The Purple Line in the News
  • Riverdale and Glenridge/New Carrollton CAT Meeting Highlights

The Purple Line in the News

Purple Line construction progress has occurred in parallel with ongoing negotiations between the state of Maryland, the concessionaire, and the subset of firms responsible for building the line. Earlier this week, Washington Post reporter Katie Shaver wrote an in-depth piece (Maryland Likely on Hook for Millions to Save Purple Line, June 13, 2020) focusing on the factors driving the negotiations, including the bigger picture for the builder and the options currently under consideration.

Two big factors in the negotiation are the payment for cost increases, such as those stemming from the lawsuit that prompted the one year delay of the project, and the handling of true uncertainty. Maryland Transportation Secretary Greg Slater emphasized in his recent briefing to the Montgomery County Council that Maryland is willing to address reasonable cost, but that the state desires a one-time adjustment rather than accepting more risk on Maryland's part.

The parties have until June 20th to reach an agreement. Typically, public information is hard to come by in the final stages of negotiation, although Delegate Mark Korman recently shared via his Twitter that the disputed amount is between $500 and $600 million, with some of the claimed costs perhaps having more support than others. Del. Korman also highlighted that it can be confusing and complicated with all the entities involved, but that there are ultimately three actors, the state which owns the project, the concessionaire that has a contract with Maryland, and the builder that has a contract with the concessionaire.

However, no matter the complexities, as the Washington Post Editorial Board plainly stated in their opinion piece earlier this spring, "The biggest losers would be those in the suburbs through which the Purple Line would pass, including supporters, opponents and commuters, who would be left with the upheaval of a major construction project roughly one-third completed. Their anger would be amply justified." (If the Purple Line project collapses now, everyone will suffer, May 29, 2020).

In case you missed Purple Line NOW's commentary regarding the current dispute and negotiations, you can read it here: Purple Line NOW News, June 3, 2020.

Stay Safe!

All of us here at Purple Line NOW hope that you and your loved ones remain healthy during this pandemic and as we reopen our state. Please, stay safe!

Share This Newsletter

Please feel free to share this newsletter - no permission from us needed! You can always find a link to our newsletter on our Purple Line NOW website which makes it easy to share with your friends, neighbors, constituents, customers, and employees.

construction2.png

CONSTRUCTION NEWS TO KNOW

Riverdale and Glenridge/New Carrollton CAT Meeting Highlights

Continuing our wrap-up of the recent Community Advisory Team (CAT) meetings, we highlight some of the work that has been done, as well as upcoming plans for the next few months. Today, we’ll focus on the combined Riverdale and Glenridge/New Carrollton CAT meeting held on May 5, 2020 and presented virtually by Gary Witherspoon, MDOT MTA Public Outreach & Communications, Deputy Project Director; Tim Pinkerton, PLTC Area 3 Construction Manager; and Shaquanna Shields, PLTC Communications Supervisor.

As always, we encourage you to either watch or read the full presentation on the MDOT MTA website which contains lots of helpful graphics and a full array of updates.

As you know, construction is underway and approximately 28% of the project is already completed. You’ll remember that the plan is to open the Purple Line in two phases:

  • Phase 1 by December 2022 with six operational stations from New Carrollton Metro to the College Park Metro
  • Phase 2 by mid-2023 when the remaining 15 stations will open

To get us started, here is an artist’s rendering of what the Riverdale Park-Kenilworth Station might look like when completed.


Courtesy of MDOT MTA and PLTP

The LRV will pass over Kenilworth Avenue and Riverdale Road at the elevated station which will help reduce traffic concerns. The presentation reminds us that the station is ADA compliant and can be accessed from a “series of stairs and/or elevators located on the southern side of the station.” The presenters also noted that the station makes use of crosswalks at track level to allow people to cross the track to get to the other platform.

Some highlights from the work that has been done since the last CAT meeting:

On Kenilworth Avenue, traffic has shifted for the road’s widening leading up to the Riverdale Road intersection. Crews have been working on sidewalk and curb reconstruction and utility relocation. More visible is the completed installation of concrete bridge girders that will support the elevated station.

On Riverdale Road, the OCS foundation installation has begun, utilities are being moved, and the retaining wall construction is continuing.

On Baltimore-Washington Parkway, crews have installed the precast concrete arched underpass section and have started building the roadway for traffic shifts back to the Baltimore-Washington Parkway bridges.


Courtesy of MDOT MTA and PLTP

Over on Veterans Parkway, we learned that the retaining walls from Riverdale south are largely complete while grading for the light rail track continues.

At Glenridge Yard, construction continues on the new Operations and Maintenance Facility (OMF) – the massive structure you can see below.


Courtesy of MDOT MTA and PLTP

Utility relocation is a massive undertaking for this project, and it continues throughout the Purple Line corridor, including this stretch of the plan. Along with those continuing relocations, work has started at the New Carrollton Metro parking lot as well as grading at the IRS building.

Looking ahead six months, the traffic shifting on Kenilworth Avenue mentioned above will continue while the installation of the elevator and stair foundations will begin at the station. Once the bridge deck is in place, crews will start the elevated portion of the station.

On Baltimore-Washington Parkway, the northbound and southbound bridges will be completed and traffic will shift for both the north and southbound direction back to the original alignment over the rail underpasses. Those temporary bridges you may have seen will be demolished.

At the Beacon Heights-East Pines Station, traffic will be shifted to the north side of Riverdale Road near Veterans Parkway this summer to facilitate additional utility relocations and light rail track work.

On Veterans Parkway, traffic shifts will occur in three phases across Annapolis Road for installation of utilities and light rail track.

In the next edition of the Purple Line News, we’ll cover the Lyttonsville, Long Branch, and University Boulevard CAT meetings. As always, we encourage you to read or watch the full presentations, especially if you live or work in the area covered.

event.png

PURPLE LINE NOW NEWS AND EVENTS

The Next Purple Line NOW Forum: Getting Ready for the First Purple Line Ride

We are working on bringing an online webinar or presentation to you later this summer, so please stay tuned for further details and a date!

Can You Help Purple Line NOW Continue Its Work?

Our work here at Purple Line NOW continues and we exist because of your donations during the year. If you would like to make a donation, you can do so by clicking on the black donate button below. We are grateful for ALL of our donors - thank you, thank you, for stepping up to help Purple Line NOW continue its work!

DONATE

Get Connected!

Make sure you are signed up for timely alerts from Purple Line NOW via our Twitter and Facebook pages, and at our website Purple Line NOW.


Purple Line NOW News - June 3, 2020

In today's edition of Purple Line NOW News, here's what you'll find:

  • The Purple Line Remains a Great Value
  • Maryland Department of Transportation Briefing to Montgomery County Council
  • Silver Spring Community Advisory Team Highlights

The Purple Line Remains a Great Value

You may have seen PLN Vice President Greg Sanders’ commentary in Maryland Matters (May 23, 2020), Purple Line Remains a Great Value, but just in case you missed it, here is the column in full:

"That companies building Maryland’s Purple Line have threatened to withdraw does indicate that costs are likely to increase and that the project will be delayed, but it does not throw the value of the project into doubt.

Geography is the strength of the 16.2-mile light rail project.

More than 150,000 people already live within a half-mile of its 21 planned stations and could use the Purple Line to travel to job centers, including the under-ten-minute trip the line would make possible between downtown Bethesda and Silver Spring. The concentration of people and jobs, combined with trains arriving every 7.5 minutes during rush hour (and options to increase that frequency to every 5 or 6 minutes), drive forecasts of about 69,300 daily riders by 2040 and 16,800 cars taken off area roads.

At a time of strained budgets, evidence of the estimated 1-to-2.2% economic growth the Purple Line will stimulate can be seen in construction that is already underway. Those projects include new, much-needed housing in Washington D.C.’s expensive inner suburbs, transit-oriented development in Riverdale, and expanded Kaiser Permanente facilities at New Carrollton.

The pandemic crisis highlights the importance of Maryland’s life sciences cluster. And, by weaving together four branches of Metrorail, the Purple Line will provide direct access to the University of Maryland and M-Square, and will improve connections to the rest of the state, including Baltimore hospitals accessible via MARC trains.

The infusion of over $1 billion in federal grants and concessionaire support for construction helps maintain the region’s economy during this pandemic. After a COVID-19 vaccine is in place and the line has opened, the Purple Line will leverage Maryland’s strengths to aid in a strong recovery. These benefits make the Purple Line a good deal even if the dispute between the state and the builders has raised the project’s costs.

Purple Line opponents triggered delays and about $150 million in cost increases when they convinced a judge to suspend construction for most of a year.

Freight rail company CSX has been slow and inflexible in negotiations, but they have at last made clear their demands. The builder has criticized Maryland’s pace with property acquisition, but we can now see progress.

Maryland reports that 28% of construction is complete.

And the Purple Line’s public-private partnership (P3) has overcome challenges that hampered Metrorail’s Silver Line construction: the concessionaire has regularly tested the quality of concrete and, where necessary, undertaken fixes at their own expense.

Still, the dispute between Maryland and the builder, if handled badly, risks compounding costs and delays. However, the private concessionaire remains committed, Maryland owns the project, and state retains a strong hand for resolving the dispute.

Costs may end up closer to estimates by the prior administration. That outcome would be in line with 2014 research by the Brookings Institution that found P3s are not a panacea, nor often the cheapest option for construction, but that P3s can provide great value over decades of operation because of performance incentives.

We encourage the state and concessionaire to resolve negotiations quickly. The best outcome — Maryland and the builder reaching a reasonable arrangement — is still on the table if a deal can be reached within the 60-90 day withdrawal period.

Meanwhile, the state and concessionaire have the option to confer with other builders, and their estimates would put the current numbers to a competitive test.

It is time to update cost and schedule estimates, but due to the Purple Line’s fundamental strengths, any fair and wise agreement will still be a bargain for the benefits it will deliver to Maryland.

— GREG SANDERS

Stay Safe!

All of us here at Purple Line NOW hope that you and your loved ones remain healthy during this pandemic. Please, stay safe!

Share This Newsletter

Please feel free to share this newsletter - no permission from us needed! You can always find a link to our newsletter on our Purple Line NOW website which makes it easy to share with your friends, neighbors, constituents, customers, and employees.

construction2.png

CONSTRUCTION NEWS TO KNOW

Maryland Department of Transportation Briefing to Montgomery County Council

On May 21, the Montgomery County Council was briefed by the Maryland Department of Transportation on the status of Purple Line construction. Greg Slater, Secretary, Maryland Department of Transportation (MDOT), and Kevin Quinn, Administrator, Maryland Transit Administration (MDOT/MTA) provided the briefing to the council. We’ll list some highlights we took away from the meeting, but you can watch the full briefing on the Montgomery County Council website.

As you know, the current group of firms building the Purple Line, the Purple Line Transit Constructors (PLTC), is threatening to leave the project if they are not granted additional funding and time to accommodate external challenges. If negotiations are not successful, the concessionaire, the Purple Line Transit Partners (PLTP), would have to find a new firm to lead the construction effort. The current plan is to open the College Park to New Carrollton portion of the line in late 2022 and the section from College Park to Bethesda (via Silver Spring) in 2023. However, last month’s news may cast those dates into doubt.

There were a lot of positives to take away from the briefing, namely that negotiations are on-going and construction is continuing with loads of visible progress. Secretary Slater stated that calls between his office and the Purple Line Transit Partners are happening daily, which was good to hear. Mr. Slater also said that the state of Maryland is acting as a “mediator” between the concessionaire and the builder. He went on to say that should negotiations fail between PLTC and PLTP, replacing the builder is something the concessionaire would initiate. We are hoping both sides find a resolution quickly.

Councilmember Evan Glass reiterated his request for more transparency in the process, especially where timeline and budget are concerned. Councilmember Tom Hucker requested more frequent updates and emphasized that this must “move forward without additional funding from Montgomery County.” Hucker also said that MDOT renegotiated Montgomery County’s contribution at the front end and he has confidence that Secretary Slater will get the support from the Governor because Montgomery Council cannot contribute more. Slater assured the Council that Governor Hogan wants this to be a success and pledged to keep everyone up to date along the way. 

Councilmember Andrew Friedson queried about the proposed timeline and reiterated that he wanted to make sure that the CCT would be able to open if it was safe and ready, even before stations were opened. He went on to say that the trail is just as important as the rail project. Secretary Slater said that opening the trail, at least in portions and when it is safe to do so, is tentatively the plan, but that he would double check and follow up. 

More of the questions can be found on the Council website, as well as the full audio/video of the briefing.

Silver Spring Community Advisory Team

The Silver Spring Community Advisory Team presentation was posted on April 28, 2020 and presented by Gary Witherspoon, MDOT MTA Public Outreach & Communications, Deputy Project Director; Carla Julian, PLTC Sr. Manager Public Affairs/Community Outreach; and Chris McRobbie, PLTC Area 1 Lead Structural Engineer.

The full presentation can be found on the Maryland Department of Transportation, Maryland Transit Administration website. Below, we offer a few highlights from the presentation, but we encourage you to see the presentations for yourselves, especially if you live or work in that particular area.

First, two artist renderings showing what the station may look like when completed:


Rendering courtesy of MDOT MTA and PLTP

Rendering courtesy of MDOT MTA and PLTP

Quite a lot of visible work has been either completed or continues, including the completion of several piers for the LRV bridge and CCT bridge and the erection of the CCT pedestrian bridge structure and LRV girders (across Colesville Road and the Metro Red Line entrance). At the Silver Spring International Middle School, crews have completed the parking lot and traffic circle.


Image courtesy of MDOT MTA and PLTP

Looking ahead six months:

Crews will begin the construction for retaining walls behind the Falkland Apartments – this will be for the LRV bridge approach, as well as along Apple Avenue to Colesville Road for the CCT.

At the Silver Spring Transit Center, the “Level 1” entrance – with signals and crosswalks was slated to be restored this spring, along with the completion of piers 6 and 7 for the LRV bridge across the “Level 2” entrance. See the presentation for a list of the many items that are slated to occur in the next half year in and around the SSTC.

Please note the partial closure of Bonifant Street (East) – the westbound direction will be closed and Bonifant (East) will operate as a one-way street eastbound. You can see very detailed work zone maps in the presentation, so if your daily commute or neighborhood is in Silver Spring, we encourage you to not only to check out those handy work zone maps, but to sign up on the website for alerts, if you haven’t already done so.

Many of you may be interested in the phasing of Wayne Avenue over Sligo Creek. As you may know, Phase 1 is scheduled to begin this summer when traffic will be reduced to one lane in each direction and shifted to the south side of Wayne Avenue. There will be no left turn from Wayne Avenue onto Sligo Creek Parkway. (See photo below)


Image courtesy of MDOT MTA and PLTP

Phase 2 will begin later this fall when the remainder of the bridge is constructed. Traffic will then shift to the north side of Wayne Avenue and will be limited to one lane in each direction, while a portion of Sligo Creek Parkway, south of Wayne Avenue will be closed. A detour will be constructed.

Here’s what the final configuration of Wayne Avenue will look like:


Image courtesy of MDOT MTA and PLTP

In the next edition of the Purple Line News, we’ll cover Riverdale Park and Glenridge stations – and then finish up with Lyttonsville, Long Branch, and University Boulevard.

event.png

PURPLE LINE NOW NEWS AND EVENTS

The Next Purple Line NOW Forum: Getting Ready for the First Purple Line Ride

We are working on bringing an online webinar or presentation to you later this summer, so please stay tuned for further details and a date!

Can You Help Purple Line NOW Continue Its Work?

Purple Line NOW still needs your donations during the year and we appreciate every penny donated. If you would like to make a donation, you can do so by clicking on the black donate button below. Thank you!

We are grateful for ALL of our donors - thank you, thank you, for stepping up to help Purple Line NOW continue its work!

Get Connected!

Make sure you are signed up for timely alerts from Purple Line NOW via our Twitter and Facebook pages, and at our website Purple Line NOW.


Purple Line NOW News - May 20, 2020

In today's edition of Purple Line NOW News, here's what you'll find:

  • Purple Line in the News
  • Highlights from the College Park Community Advisory Team Presentation

Stay Safe!

All of us here at Purple Line NOW hope that you and your loved ones remain healthy during this pandemic. Please, stay safe!

Share This Newsletter

Please feel free to share this newsletter - no permission from us needed! You can always find a link to our newsletter on our Purple Line NOW website which makes it easy to share with your friends, neighbors, constituents, customers, and employees.

construction2.png

CONSTRUCTION NEWS TO KNOW

Purple Line in the News

We hope you had a chance to read the letter to the editor in the Washington Post (May 15, 2020) from long time Purple Line supporter Brian Ditzler of Silver Spring. Purple Line NOW will also have an official commentary coming out in the next week, so keep your eyes peeled for that. Make sure you are signed up for timely alerts from Purple Line NOW via our Twitter and Facebook pages, and at our website Purple Line NOW.

Highlights from the College Park Community Advisory Team Presentation

The College Park Community Advisory Team (CAT) presentation was posted on the MDOT MTA website on April 21, 2020. The information for the presentation was provided by Gary Witherspoon, Public Outreach & Communications Deputy Project Director; John Koussis, PLTC Area 3 - Segment 6 - Project Engineer; and Shaquanna Shields, PLTC Communications Supervisor.

With these new CAT meeting presentations comes a series of artist renderings of the stations - not exact replicas, but enough to give us a sense of what the stations may look like. As the slide notes, both the Adelphi Road and College Park metro are center platforms, which means, "the tracks run on either side of the platform with the shelter in the center."


Rendering Courtesy of MDOT MTA and PLTP

As of the date of the presentation, approximately 28% of the construction on the Purple Line is complete -- almost a third done and dusted! You can see the presentation for yourself on their website, but here are some highlights, with thanks to MDOT MTA and PLTP for providing the information to the public.

Starting with Campus Drive West, the ever-present utility relocations have continued, along with storm drain work, and installation of a temporary signal at the intersection of the University Boulevard/Campus Drive and Adelphi Road/Campus Drive intersections. At Campus Drive East, sidewalk demolition has started.

At the University of Maryland, along with the utility relocations, construction has started for the new “M” (while leaving the existing “M” in place for now.) In and around the College Park Metro, the bus loop remains closed and a water line relocation at the station has begun. On River Road, the retaining wall south of the College Park Metro has started and the bridge for the Light Rail over the Anacostia Northeast Branch continued. The girder erection was completed in February.


Slide Courtesy of MDOT MTA and PLTP

Looking ahead to the next six months, the temporary signal installation and traffic shift at University Boulevard and Campus Drive should be completed and Campus Drive (eastbound) between Adelphi Road and Presidential Drive will be widened to make way for the Purple Line station. In and around campus, the new “M” and removal of the existing traffic circle will be completed. Along Campus Drive East, the new pump station construction should be completed this summer and the segment between Paint Branch Trail and River Road will be fully closed to facilitate major road work along that portion.

The following slide details the Campus Drive East detour that was to begin mid-April. The closure will be in effect for approximately 15 weeks with local access (only) permitted.


Slide Courtesy of MDOT MTA and PLTP

We'll be bringing you highlights from other CATs in future newsletters, including Silver Spring, University Boulevard, Riverdale Park, Lyttonsville/Woodside, and Glenridge!

event.png

PURPLE LINE NOW NEWS AND EVENTS

The Next Purple Line NOW Forum: Getting Ready for the First Purple Line Ride

We are working on bringing an online webinar or presentation to you later this summer, so please stay tuned for further details and a date!

Can You Help Purple Line NOW Continue Its Work?

Purple Line NOW still needs your donations during the year and we appreciate every penny donated. If you would like to make a donation, you can do so by clicking on the black donate button below. Thank you!

DONATE

We are grateful for ALL of our donors - thank you, thank you, for stepping up to help Purple Line NOW continue its work!

Get Connected!

Make sure you are signed up for timely alerts from Purple Line NOW via our Twitter and Facebook pages, and at our website Purple Line NOW.



Follow Us

 Follow Us on Facebook Follow Us on Twiter

Donate Now Contact Us e-News